If you're planning a demolition in the City of San Diego, the permit isn't the only paperwork standing between you and a clear lot. Most demolition projects also fall under the City's Construction and Demolition (C&D) Debris Diversion Deposit Program, which means you pay a refundable deposit up front and only get it back if you can prove your debris was recycled, reused or donated instead of landfilled.
At San Diego Deconstruction & Demolition (SDD), C&D compliance is built into how we work. Below we break down how the City's C&D debris reporting works, what it costs, where projects lose their deposits, and how our team handles the tracking and documentation so you don't have to.

What Is San Diego's C&D Debris Diversion Deposit Program?
The City of San Diego adopted its C&D Debris Diversion Deposit Program on July 1, 2008, under San Diego Municipal Code §66.06. Its goal is to keep recyclable construction and demolition material out of local landfills and extend the life of the Miramar Landfill.
The ordinance applies to most construction, demolition and remodeling projects that require a building, combination or demolition permit. In plain terms, here is how it works:
1. You submit a Waste Management Form (Part I) estimating how much debris the project will generate.
2. You pay a refundable C&D debris recycling deposit when the permit is issued.
3. You divert at least 65% of your project debris (by weight) through recycling, reuse or donation.
4. You submit weight tickets and documentation within 180 days of final inspection to get your deposit back.
The City will not issue the permit until the Waste Management Form is submitted and the deposit is paid, so C&D planning has to happen before demolition starts, not after.
How Much Is the C&D Debris Deposit for a Demolition?
The deposit is based on project type and square footage. According to the City's current deposit table:
Project type | Deposit | Square footage covered | Deposit range |
Demolition, residential new construction, non-residential alterations | $0.40 per sq. ft. | 1,000 to 100,000 sq. ft. | $400 to $40,000 |
Non-residential new construction | $0.20 per sq. ft. | 1,000 to 50,000 sq. ft. | $200 to $10,000 |
Residential alterations | $1,000 flat | 1,000 to 6,999 sq. ft. | $1,000 |
Example: Demolishing a 2,500 sq. ft. house in the City of San Diego means a C&D deposit of about $1,000. Tearing down a 20,000 sq. ft. commercial building means about $8,000. That money is fully refundable, but only if the diversion is achieved and properly documented.
Some work is exempt, including roofing-only projects, foundation repairs, projects that only need an electrical, plumbing or mechanical permit, projects that don't require building plans, and any project where the deposit would be under $200. Always confirm with the City's current deposit table, since the rules are updated periodically.

What Diversion Rate Does a San Diego Demolition Need to Hit?
For projects with permits issued on or after July 1, 2016, the City requires 65% diversion by weight. Projects permitted before that date were held to 50%.
The Municipal Code also includes a future 75% tier, which takes effect only after specific conditions are met, including a qualifying certified mixed-debris facility and 30 days of public notice from the City. Projects should be planned around the rate in effect when the permit is issued, and we track this so our clients aren't caught off guard.
The refund is proportional: if your project falls short of the required rate, you only get back a portion of your deposit. If the paperwork is never submitted, the entire deposit is forfeited to the City.
How C&D Debris Reporting Actually Works, Step by Step
This is the part most property owners and even some general contractors underestimate. The City doesn't take your word for it. Diversion must be proven with documentation.
Before demolition: the Waste Management Form (Part I)
The Waste Management Form asks for an estimate of the C&D debris your project will generate, in tons, broken out by material type (concrete, wood, metal, drywall, mixed debris and so on). Material that can't be weighed is estimated using the City's C&D Debris Conversion Rate Table. The form also asks which City-certified recycling facilities will receive the debris, because only certified facilities count toward your refund.
During Demolition: Hauling to Certified Facilities
Every load that leaves the site needs to go somewhere that counts. That means:
• Certified C&D recycling facilities listed in the City's Certified Construction & Demolition Recycling Facility Directory
• Source-separated material (clean concrete, asphalt, metal, green waste) going to facilities that recycle those streams at high rates
• Mixed C&D debris going to certified mixed-debris processors, which are credited at their certified diversion rate
• Salvaged and donated items documented with receipts and photos
Each load generates a weight ticket. Those tickets are the backbone of your C&D report, and losing them is the fastest way to lose a deposit.
After final inspection: Part II and the refund request
Within 180 days of final inspection, the permit holder submits the Waste Management Form Part II along with all trash and recycling weight receipts and supporting documentation. The City compares the diverted tonnage against total tonnage, calculates your diversion rate and refunds your deposit accordingly.

The City vs. the County: Different Rules, Different Paperwork
Where your property sits matters. If your project is in unincorporated San Diego County rather than the City of San Diego, you are under the County's C&D ordinance instead, which works differently:
• 90% of inert materials (concrete, asphalt, soil, rock) and 70% of all other materials must be recycled
• A refundable performance guarantee of $0.40 per sq. ft. applies to covered construction and demolition projects
• Projects must submit a Debris Management Plan, keep a Daily Log on site and file a Debris Management Report at completion
Other incorporated cities in the county, such as Chula Vista, Carlsbad, Oceanside and Escondido, run their own C&D programs, and California's CALGreen building code sets a statewide baseline as well. Part of our job is knowing which set of rules applies to your address before the first truck rolls.
Where San Diego Demolition Projects Lose Their C&D Deposits
In our experience, deposits are rarely lost because the debris wasn't recycled. They're lost because the recycling wasn't documented. The most common problems:
• Missing weight tickets. A load gets hauled and the ticket never makes it back to the file.
• Non-certified facilities. Debris dumped at a facility that isn't on the City's certified list doesn't count, even if it was recycled.
• Mixed loads coded wrong. Mixed C&D debris that isn't identified correctly at the scale may be recorded as trash.
• Blown deadlines. The 180-day clock starts at final inspection, and on long projects that date sneaks up.
• Wrong party holding the paperwork. The owner, the GC and the demo sub each assume someone else is filing.
• Clean concrete mixed into general debris. Concrete is heavy and almost fully recyclable. Contaminating it drags your diversion rate down fast.
How San Diego Deconstruction & Demolition Handles C&D Reporting
We built our company around a deconstruction-first approach, which puts us well positioned to hit San Diego's diversion requirements. Here's how C&D compliance fits into our process.
1. Accurate debris estimates up front
We walk the site and estimate debris by material type so the Waste Management Form reflects reality. Good estimates mean fewer surprises and a cleaner report at the end.
2. Salvage before we demolish
Before heavy equipment comes in, our crews salvage reusable lumber, fixtures, cabinetry, doors and architectural elements. Salvaged and donated material counts toward diversion and keeps usable materials in circulation.
3. Source separation on site
Concrete, asphalt, metals and green waste are separated whenever the site allows. Clean, separated streams recycle at much higher rates than mixed loads, which is the single biggest lever for clearing the 65% threshold.
4. Certified facilities only
We haul to facilities on the City's certified directory and make sure loads are identified correctly at the scale, so every ton counts toward your refund.
5. Every weight ticket, tracked and organized
We collect and organize weight tickets for every load leaving the site. Upon request, we provide our clients with C&D recycling reports, weight tickets and supporting documentation needed for City and local jurisdiction waste diversion requirements, ready to attach to your Part II submission.
6. Permit coordination
Need help with the permit itself? We offer demolition permit acquisition as a separate service, which keeps the permit, the C&D deposit and the diversion reporting under one roof.
Why This Matters Beyond Getting Your Deposit Back
Getting the deposit refunded is the obvious win, but strong C&D practices pay off in other ways too. Recycling heavy materials like concrete is often less expensive than landfill disposal. Clean documentation helps projects pursuing green building certifications. And for developers and GCs, a demolition partner who handles C&D reporting means one less thing to chase at closeout.
C&D debris makes up a large share of what goes to landfills in our region. The County estimates it at roughly 34% of landfilled waste, over a million tons a year countywide. Every load we divert is material that doesn't fill up Miramar.
Frequently Asked Questions About C&D Debris Reporting in San Diego
Do I need to pay a C&D deposit for a demolition permit in San Diego?
In most cases, yes. Demolition projects of 1,000 sq. ft. or more in the City of San Diego typically require a refundable deposit of $0.40 per sq. ft., paid at permit issuance along with a Waste Management Form.
How much of my demolition debris has to be recycled?
For City of San Diego permits issued on or after July 1, 2016, at least 65% of project debris by weight must be diverted through recycling, reuse or donation. Unincorporated County projects require 90% of inerts and 70% of other materials.
How long do I have to get my C&D deposit back?
You must submit your weight receipts and documentation within 180 days of the project's final inspection. Deposits that aren't claimed are forfeited to the City.
What happens if my project doesn't hit 65%?
The refund is proportional to the diversion achieved, so you'll receive a partial refund rather than the full deposit.
Does salvaged or donated material count toward diversion?
Yes. Reused and donated materials count, as long as they're documented with receipts and photos.
Who is responsible for C&D reporting, the owner or the contractor?
The permit holder is ultimately responsible for the refund request. In practice, the demolition contractor generates most of the documentation, which is why it matters to hire one who tracks it carefully. SDD provides C&D reports and weight tickets to clients on request.
Do you handle demolition outside the City of San Diego?
Yes. We serve all of San Diego County and work within whichever jurisdiction's C&D rules apply to your project.
Plan Your San Diego Demolition With C&D Compliance Built In
C&D debris reporting doesn't have to be a headache, or a forfeited deposit. San Diego Deconstruction & Demolition is a licensed C-21 demolition contractor (CSLB #1082669) serving homeowners, general contractors and developers throughout San Diego County. From permit coordination and salvage through final haul-off and C&D documentation, we keep your project on schedule and your debris out of the landfill.
Request an estimate: call (619) 273-3467, email info@sandiegodemolition.com or visit sandiegodemolition.com.
This article is for general information. C&D requirements and deposit amounts are set by each jurisdiction and change over time. Confirm current requirements with the City of San Diego Environmental Services Department or your local jurisdiction before starting a project.




Comments